Wed., Nov. 18 Public meetings: Forest Home Township Parks & Recreation Commission (5:15 p.m.)Central Lake Township Board (7 p.m.) Dates come from each office and can change.

Dec. 2 hearing A township notice sets the Forest Home Planning Commission’s Dockside Point hearing for Wed., Dec. 2, 6 p.m., in the Bellaire High School PAC room. It was first set for Nov. 4. As of Nov. 18 the township site had no minutes of that meeting, and minutes through Oct. 7 record no vote. Milton Township’s Nov. 4 Planning Commission minutes were not posted as of Nov. 13. Pages: Dockside VillageCairn ClubDockside hearing set for Dec. 2, 6 p.m., at Bellaire High School. Nov. 4 minutes: Dockside VillageCairn Club

The Torch Lake Observer
Milton Township · Decision pending; listed for the Planning Commission’s Dec. 2 meeting

16 rental homes off Chippewa Trail

12985 Anchor Drive, Rapid City, a new private drive off Chippewa Trail (parcel 05-12-101-008-70) · Map

By Observer Staff · Published Nov. 2, 2026 · Updated Nov. 7, 2026 · Status as of Nov. 10, 2026

EmailTextFacebook

What would be built

Sixteen small single-family homes for rent, clustered on five acres of farm-zoned land under the township’s 2024 rules for “Planned Residential Developments.” Applicant Tad Dowker told the Planning Commission on Sept. 2 that he employs 75 to 90 people and that the “end goal is affordable housing and getting people a place to live.” He said his goal is to take care of his employees, with any extra homes rented to others. His attorney said the leases would comply with fair-housing law and, asked whether employees would take priority, said the homes “would be available to whomever would want to apply.” Most speakers in that night’s public comment opposed the project; at least one spoke for it. In Dec. 2025 Dowker applied for a zoning amendment to clarify lot size and density. The Planning Commission recommended it March 4, 2026; the township board denied it May 18, 2026, and adopted a temporary moratorium on new applications of this kind on farm land. After a hearing to correct a typo, the board adopted the moratorium again on Sept. 21, effective Oct. 2 and running until June 21, 2027. Dowker filed his application on June 2, 2025, before the moratorium; at the Sept. 2 meeting the township attorney said the moratorium was “not in place,” and the township planner said this is a pending application.

16rental homes
5acres (the lot is about 6)
728–1,120square feet per home
1story

Who is applying

Tad Dowker, the applicant, who owns the land according to the county parcel roll. His attorney also spoke for the project at the Sept. 2 meeting.

Water and sewage

A private community well, with a second well for backup, and on-site septic systems (the planner calls them “two-unit septic systems”). The township planner’s Sept. 29 memo says the applicant has provided preliminary approval from the Health Department of Northwest Michigan and “well testing from EGLE.”

  • The township’s rules cap this kind of development at 5 acres. The lot is about 6, so Dowker has applied for a lot-line adjustment that would cut it to 5 acres, with the community well on an easement.
  • At the Sept. 2 meeting, Chairman Warner said of the wells outside the 5 acres, “I do not see a clear path to correcting this”; the planner said the township approves special use permits with conditions “on a regular basis.” Commissioner Hefferan said he “does not remember approving a project with so many conditions”; the township attorney said “it does happen.” The planner’s Sept. 29 memo says staff found the application “as submitted is complete and complies with all current zoning ordinance standards with conditions of approval,” and lists 10 proposed conditions.

Township planner’s memo, Sept. 29, 2026; Planning Commission minutes, Sept. 2, 2026; Antrim County parcel roll.

The approvals it needs

  1. Township

    Special use permit for the development (SUP 2025-03)

    Pending since the application

    Applied June 2, 2025. The commission found it incomplete in Sept. 2025. The planner’s timeline says the applicant submitted the outstanding materials on Nov. 11, 2025, with lot size the only open item, then sought the zoning amendment described above. A public hearing was set for Oct. 7, 2026; as of Nov. 10 we have not found minutes for that meeting. The Nov. 4 agenda lists “Continued Discussion” for Dec. 2. Planner’s memo (Oct. 7 packet) →

  2. Township

    Lot-line adjustment to bring the lot to 5 acres

    Application received

    Received by Sept. 29, 2026, according to the planner’s memo.

  3. Health Dept.

    Community well and septic systems

    Preliminary approval

    Preliminary approval from the Health Department of Northwest Michigan, plus “well testing from EGLE,” according to the planner’s memo.

  4. County Road Commission

    Private access drive (“Anchor Drive”)

    Approved

    The Antrim County Road Commission approved the drive’s location, design and name, and the fire department approved the access design, according to the planner’s memo.