Dockside Village
6326 and 6340 Old Torch Lake Drive, on Clam Lake where it meets Torch Lake · Map
Status as of Nov. 1, 2026
Wed., Nov. 4, 2026, 7 p.m. · Public hearing before the Forest Home Township Planning Commission · Township Hall, 321 N. Bridge St., Bellaire
The hearing was held Nov. 4. We will report the outcome when the minutes are posted.
What would be built
The Dockside restaurant and watersports buildings would be torn down and replaced by one three-story building: an expanded restaurant, a bakery-café, retail and five condominiums, under a 71-foot “lighthouse” tower. It is requested as a Planned Unit Development, a zoning deal negotiated with the township.
Who is behind it
Applicant: Nick McMullen / McMullen Properties, per the hearing notice. The site has been owned since 2019 by Aqua Dome Car Wash LLC, a Florida company formed in 2017 as McMullen Properties LLC. A related company, Steiner Pit LLC, owns the land behind the site, now marketed as “BaseCamp at Torch Lake” (18 homes).
Where the sewage goes
A private sewage plant on the land behind the site, shared with BaseCamp’s 18 homes. Treated sewage would soak into the ground. A nonprofit, the Steiner Pit Sewer Association, would own and run it. The township has said it will not take responsibility for the system (letter of June 5, 2026).
| For | Gallons a day | Share of capacity |
|---|---|---|
| Dockside restaurant (figured at 200 seats) | 7,800 | |
| BaseCamp’s 18 homes | 5,400 | |
| Dockside watersports | 1,575 | |
| The 5 condos, bakery and retail | 0 |
The site plan shows 305 restaurant seats, not the 200 the sewage design assumes.
Engineer’s sewage flow calculations, Apr. 11, 2026.
The approvals it needs
- Township
Zoning approval (Planned Unit Development)
Waiting on the Planning Commission
Submitted Sept. 18, 2026. Public hearing Wed., Nov. 4, 2026. PUD submission →
- State (EGLE)
Groundwater discharge permit for the sewage plant HQN-8FKV-VNJY4
In process, no permit179 days
Application received May 6, 2026. The public notice that must come before any permit has not posted. State record, as we saved it →
- State (EGLE)
Construction permit for the sewage system HQN-8D5K-23FJ5
On hold
Application received June 23, 2026. State record, as we saved it →
- State (EGLE)
Marina permit (docks on the lake) WRP048069
Issued
Issued Feb. 23, 2026, good through Feb. 23, 2031. It is held by the rental operator, not the applicant. The permit →
- County
Building and soil-erosion permits
Not checked yet
These come later in the process. The developer plans demolition in fall 2027.
The documents
- PDFPUD submission, Sept. 18, 2026
- PDFOfficial hearing notice
- PDFSewage flow calculations, Apr. 11, 2026
- PDFTownship letter declining sewer responsibility, June 5, 2026
- PDFMarina permit WRP048069, Feb. 23, 2026